The project is for Development of Roads for Division 5B, West Kochi. CSML intends to develop 12 roads in West Kochi (3.302 Km).
The scope of work includes developing the existing roads mentioned above by upgradation and augmentation of foot path, pavements, provision of cycle lanes, providing Road Markings, Street Furniture, Bus bays, Street Landscaping works, utility trenching/ducting works, Construction of new drains and restoration of existing drains as per site requirements, foundation for streetlight poles, monopoles, along with operation maintenance of landscaping works.
PROJECT COST | Rs. 6.29 Crores |
STATUS | Not Completed |
START DATE | 11-Dec-2020 |
EXPECTED COMPLETION | 11-Dec-2021 |
PHYSICAL PROGRESS (%) | 4% |
FINANCIAL PROGRESS (%) | 0% |