Development of Roads for Divisions 1 & 2 West Kochi

Previous
Next

Development of 14.06 Km of 53 Other roads in West Kochi 2 wards in ABD. The Other roads will be developed with upgradation of drainage facilities, provision of footpath (as per standard and space available) and surface improvement with bituminous surfacing or interlocking paver blocks wherever required.

PROJECT COST

Rs. 34.73 Crores

STATUS

Not Completed 

START DATE

04-Oct-2019

EXPECTED COMPLETION 

04-Nov-2021

PHYSICAL PROGRESS (%)

49%

FINANCIAL PROGRESS (%)

37%